Key things to remember

When we contract with a Supplier they need to maintain a level of Performance that meets the requirements of both CBRE and our Client.  Whe the Performance drops, there may be a need for a performance review.  Carrying out any such review must always be done during the contract term.    

Why?  This ensures the budget versus actual performance is re-assessed in order to potentially make adjustments for the remaining tenure of the Supplier partners contract term, if not already completed annually. 

Why do we need to manage our Suppliers Performance ?

What drives the need for a PIP

(Performance Improvement Plan) ?

1. Early Supplier engagement is key to a successful outcome for Performance improvement
2. Present FACTS, not emotive ideas
3. Ensure a measurable process is in place to manage performance
4. Ensure the supplier understands the expectations of the contract and its required outcomes
5. Openly discuss issues in regular meetings to mitigate any escalations, where practical
6. Form the right relationships with the Supplier partners to foster best-in-class practices

How do we implement a PIP ?

1st Phase - Formal written warning:

The Global Procurement Solutions lead (or account Procurement leader) will submit a formal written warning to any Supplier partner under any one or combination of the following conditions:

  1. One quarterly performance rating with the overall aggregate supplier score and / or Customer Satisfaction score of less than 3.0
  2. Net Promoter scores of less than 10.0

The Global Procurement Solutions Lead (or account Procurement leader) will review the Supplier partner performance within 6 months of any supplier receiving a warning

 

2nd Phase - Formal Supplier Performance Improvement Plan (PIP):

A Supplier will assist in managing a PIP under any one or combination of the following conditions:

  1. Two (2) consecutive quarterly performance ratings with an overall supplier score and / or Customer satisfaction score of less than 3.0
  2. Two (2) consecutive Net Promoter scores of less than 10.0

Confidential & Proprietary | 2024 CBRE Inc.

Back to Top

Useful Links

Resource Library

Managing Supplier Performance

Resource Library

Page 1 of  4

Page 2 - Conduct Root Cause Analysis
Page 3 - Supplier Partner PIP
Page 4 - PIP Process Steps
Page 1 - Manage Supplier Partner Performance

1:

 Poor KPI Performance

2:

 Not adhering to the SLA

3:

 Financially underperforming

4:

 Low Customer Satisfaction

5:

 External Factors

6:

 Scope change

CBRE PIP Process
Corrective Action Plan
Root Cause Analysis Template
Risk Assessment Template

RL-009 Ver 1.0 (Jan 24)

Root Cause Analysis (RCA) Guideline

Confidential & Proprietary | 2024 CBRE, Inc.

Useful Links

Resource Library

Conducing Root Cause Analysis (RCA)

Resource Library

Page 2 of  4

Back to Top
Page 1 - Manage Supplier Partner Performance
Page 3 - Supplier Partner PIP
Page 4 - PIP Process Steps
Page 2 - Conduct Root Cause Analysis

Root Cause Analysis (RCA) is an activity that must be followed to address a problem or non-conformance which has been identified, often through an internal or external audit.

Root Cause Analysis investigates why a problem or non-conformance has occurred and gets to the “fundamental” root cause of the problem and enables us to find effective solutions and therefore prevents its recurrence.

Why complete a RCA ?

Root Cause Analysis (RCA) is an activity that is followed to address a problem or non-conformance that has been identified, often through an internal or external audit. 

Root Cause Analysis investigates why a problem or non-conformance has occurred and gets to the “fundamental” root cause of the problem and enables us to find effective solutions and therefore prevents its recurrence.

What does a RCA address ?

1:

Resolves Customer

complaints

2:

Deals with Equipment

failures and issues

3:

Manages Non-Compliance

4:

Supports Corrective Actions

Implementing the RCA (5 Steps)

Transitioning

of Supplier

Program Optimisation - Change of SOW

Renewed Savings Directives

Cost-Plus Supplier overspending

Contract sunsets within

6 months

5

4

3

2

1

Improve Data Analytics

Accelerate Digital Transformation

Reduce Spend Cost

Manage & Mitigate Inflation

Reduce Procurement Risk

5

4

3

2

1

Implement Solutions

5

Identify Root Cause

4

Identify factors that caused the issues

3

Collect Data

2

Define the Problem

1

What do you see happening?

What are the symptoms?

How long has the problem existed?

What is the impact?

What events lead to the problem happening?

What is the reason the problems occurred?

What actions can prevent the problem  occurring again?

How will the solution be implemented?

Who is responsible to complete?

The RCA Flow Chart

CBRE PIP Process
Corrective Action Plan
Root Cause Analysis Template
Risk Assessment Template

RL-009 Ver 1.0 (Jan 24)

Supplier  Performance Improvement Process (PIP)

Is...

  1. A strategic Supplier corrective action process
  2. Defined service improvement objectives and timelines
  3. Championed by supply chain leadership, but managed by the supplier partner
  4. A measurement of Supplier improvement resulting in sustainable service quality
  5. A regular cadence of reviews to discuss Supplier progress to plan
  6. A final disposition of Supplier partner performance used to determine the Supplier’s status with CBRE
  7. A process that can be launched at the account level or central operations support team

Is NOT...

  1. A day-to-day Supplier quality management process
  2. An emotionally driven process
  3. A tool to beat down Supplier's into conformance
  4. A process that has no end or result
  5. Measured by subjective data

​

Responsibility

Performance:   Account Teams

KPI's Source:   Supplier

Responsibility

Account team Procurement Leader

Country Lead

Procurement Platform Lead, or Divisional Procurement Lead

Responsibility

Supplier supported by appropriate CBRE team

Responsibility

KPI Source:   Supplier 

Performance:   Account teams

Refine corrective action:  CBRE 

Responsibility

KPI Source:   Supplier 

Performance:   Account teams

QBR:   Category Managers

Measure

Define

Improve

Monitor

Sustain

  • Poor overall Customer Satisfaction ratings
  • Poor Supplier Net Promoter Score
  • KPI's below expectations
  • Establish service issues
  • Desired outcomes
  • Performance Improvement Team & Champions
  • Identify "Root Cause" using best practice tools
  • Brainstorm improvement ideas
  • Develop & execute improvement plan
  • Monitor progress and affects on changes
  • Evaluate data trends in response to changes
  • Adjust corrective action as needed
  • Use of KPI's to manage service delivery 
  • Cadence of Performance feedback-KPI alignment
  • Cadence of Business reviews-align client expectations

Establish Service

Issues

Project Plan

Implement

Improvement Plan

Measure

Improvement Process

NEW QUALITY

CULTURE

Confidential & Proprietary | 2024 CBRE, Inc.

Useful Links

Resource Library

Supplier Performance Improvement Process (PIP)

Resource Library

Page 3 of 4

Back to Top
Page 1 - Manage Supplier Partner Performance
Page 2 - Conduct Root Cause Analysis
Page 4 - PIP Process Steps
Page 3 - Supplier Partner PIP
CBRE PIP Process
Corrective Action Plan
Root Cause Analysis Template
Risk Assessment Template

Review Objective evidence of poor performance over time including prior Corrective Action efforts

RL-009 Ver 1.0 (Jan 24)

Next Steps- Implementing the PIP

Confidential & Proprietary | 2024 CBRE, Inc.

Back to Top

Resource Library

Performance Improvement Process Steps

Resource Library

Page 4 of  4

Page 1 - Manage Supplier Partner Performance
Page 2 - Conduct Root Cause Analysis
Page 3 - Supplier Partner PIP
Page 4 - PIP Process Steps

1

Identify and document improvement Objectives, desired outcomes and Timing

2

Identify Key Stakeholders which include the Supplier partner

3

Identify Performance Improvement Team and Team Champions

4

Gain sponsorship and approval from Supply Chain key Stakeholders to launch a 90 day PIP

5

Complete a Charter to communicate the PIP Objectives, timing, support, tools and outcomes

6

Communicate the launch of the 90 day PIP and explain the overall process

7

Schedule meetings with all Stakeholders to launch the PIP

8

Request Supplier to initiate the 90 day PIP

9

Supplier to create a progress Dashboard that communicates the overall improvement status

10

Communicate agreement on timing, reporting and expected outcomes to all

11

Plan for final review after 90 days and any next steps

12