9-12 Months out

The effective planning of a Food Service supplier change is fundamental as the RFP process takes a significant amount of time, effort and resource to implement.

Identifying available support resources may also prove challenging. Advanced planning ensures a smooth and effective process. Supplier Operating Standards should be used within all Food Service Supplier RFP’s and subsequent supplier contracts. Allowing sufficient time to manage an initiative will ensure that an effectively engineered solution is identified, robustly validated and a "best-fit, best-value" supplier partner as an integral part of an operationally, financially and administratively sustainable program.

  • End of the contract term or request from Client to change
  • Unsuccessful supplier re-bid for the services
  • Supplier performance issues - early termination by CBRE / Client
  • Supplier commercial viability - early termination by supplier/ CBRE / Client
  • Change of supplier ownership through acquisition or Supplier goes into receivership

1. Typical Supplier Change Drivers

FS-021 Ver 2.1 (Aug 23)

Engage Client and key stakeholders

identify roadblocks, discuss with stakeholders

Brief suppliers, prepare shortlist, brief sourcing

Agree Sourcing process and draft SOS / SOW

Prepare RFP and Timeline

6 Months out   

Issue the RFP

Review RFP and Commercials, negotiate as required and select supplier 

Obtain Client and Internal approvals, legal etc,.

Award Contract, service notices to incumbent, prepare transition plan

Communicate to all stakeholders

3 Months out

Align existing supplier with incoming supplier to ensure a seamless transition

Agree and align to on-site RACI

Approve tariff strategy, selling prices, menu design and content, etc.

Finalise equipment requirements and supplier partner investment

Prepare Marketing communications

1 Month out

Communicate transition to all parties and socialise information

Finalise updates on all commercial requirements 

Arrange signage, website and IT set-up

Ensure TUPE (Transition Undertaking Protection of Employment) processes are in place

GO - LIVE

Food Services

Project Timing

BID